Legalization of Lower Floor

El Granada, CA​
Fee for the stamped drawings and calculations:
~$3500
Turnaround time to deliver the structural plans:
3 weeks
Time until permit approval:
2 months
Project Scope:

Lowered the finished floor level of existing lower floor slab / foundation​

Legalized the entire unpermitted lower floor by preparing full structural drawing and calculation sets for City approval​